(b) If, after the grant agreement is executed and before the final payment of the allowable project costs is made under §151.63, it appears that the sponsor inadvertently or unknowingly failed to comply with paragraph (a) of this section as to any item, the Administrator—
(1) Makes or obtains an appraisal of the item, and if the appraised value is less than the value placed on the item in the project application, notifies the sponsor that it may, within a stated time, ask in writing for reconsideration of the appraisal and submit statements of pertinent facts and opinion; and
(2) Adjusts the U.S. share of the project costs to reflect any decrease in value of the item below that stated in the project application.
[Amdt. 151–34, 34 FR 12883, Aug. 8, 1969]
NEXT: Sec. 151.25 - Procedures: Application; information as to property interests.
PREVIOUS: Sec. 151.23 - Procedures: Application; funding information.